Beasie Rd Extension (River Rock Blvd just north of Racquet Club Dr)
Expected No Lane Closures: Monday Through Friday: Incidental works continues. Appropriate traffic controls will be in place.
Joe B Jackson Pkwy at Butler Dr/Elam Ln
Expected Lane Closures: Monday through Friday, 8:30 AM – 3:30 PM: Contractor for a private development will be installing turn lanes on Joe B Jackson Pkwy. There will be traffic shifts and interruptions on Joe B Jackson Pkwy. Appropriate traffic controls will be in place.
Compton Ln Turn Lane Improvement Project just east of Emery Ln
Expected Lane Closures: Monday, 8:30 AM – 3:30 PM: Contractor for a private development will be paving the turn lanes on Compton Ln. There will be lane shifts and minor interruptions. Appropriate traffic controls will be in place.
Left Turn Lane Installation Work (Burnt Knob Rd just east of Veterans Pkwy)
Expected Lane Closures: Monday through Friday, 8:30 AM – 3:30 PM: Contractor for a private development will be installing left turn lanes on Burnt Knob Rd just east of Veterans Pkwy. There will be lane shifts and traffic interruptions. Appropriate traffic controls and detours will be in place.
New Commercial Driveway Entrance Work (Veterans Pkwy just north of Franklin Rd)
Expected Lane Closures: Monday & Tuesday, 8:30 AM – 3:30 PM: Contractor for a private development will be installing new commercial entrance driveway on Veterans Pkwy just north of Franklin Rd. Southbound traffic on Veterans Pkwy will be reduced from two lanes to one lane. Appropriate traffic controls and detours will be in place.
Sewer Installation/Tie-in Work at Victory Station Way just east of Swanholme Dr
Expected Lane Closures: Tuesday through Thursday, 8:30 AM – 3:30 PM: Contractor for a private development will be installing sewer line and tie-in on Victory Station Way. There will be lane shifts and minor traffic interruptions on Victory Station Way. Appropriate traffic controls will be in place.
Sewer Installation Paving Work on Riverrock Blvd just north of New Salem Hwy
Expected Lane Closures: Thursday & Friday, 8:30 AM – 3:30 PM: Contractor for a private development will be paving a sewer line patch on Riverrock Blvd. There will be lane shifts and minor traffic interruptions on Riverrock Blvd. Appropriate traffic controls will be in place.
Annual City Street Paving
Expected Lane Closures: Monday through Friday, 9:00 AM – 3:00 PM: City contractor will be performing construction work at the following streets:
1. Eastbound Medical Center Pkwy between Asbury Rd and Conference Center Blvd (roadway widening, median extension and traffic signal work)
2. Old Lascassas Rd (milling work)
3. Dusan Blvd, 3173 Holsted Dr, 4209 Stark St, 618 Gallant Way, 1402 Eventide Dr, Gunnerson Ave & Rocky Ln (sewer rehabilitation work)
Expect lane shifts and traffic interruptions. Appropriate traffic controls will be in place.
TDOT Resurfacing Projects
(Source: TDOT)
RUTHERFORD COUNTY I-24
The resurfacing on I-24 from near the Stones River to east of the CSXT Railroad.
· Nightly, 8 p.m. – 5 a.m., There will be alternating lane closures on I-24 EB and WB for milling and paving activities. (MM 78-82)
RUTHERFORD COUNTY SR 99
The grading, drainage, construction of retaining walls, signals and paving on SR-99 (New Salem Hwy) from near I-24 to SR-96 (Old Fort Pkwy)
· Daily, 9 am -3 pm: There will be periodic flagging operations for construction activities.
RUTHERFORD COUNTY SR 266
The grading, drainage, construction of two concrete bulb tee beam bridges, signals, and paving on SR-266 (Jefferson Pike) from SR-102 (LM 5.0) to E. of I-840 (LM 9).
· Daily, 9 a.m. – 3 p.m., There will be periodic flagging operations for construction activities.
RUTHERFORD COUNTY I-840
The resurfacing on I-840 from near I-24 to near the West Fork Stones River.
· Nightly, 8 p.m. – 5 a.m., There will be alternating nightly lane closures on I-840 EB and WB for milling and paving activities (MM 50 – 55).
RUTHERFORD COUNTY SR 1
The resurfacing on U.S. 70S (from south of Ash Street to near South Rutherford Boulevard)
· Nightly (excluding holiday restrictions), 8 p.m. – 5 a.m., There will be periodic flagging operations for construction activities.
RUTHERFORD COUNTY SR 10
Intersection improvements on SR 10 (US 231) from south of Rock Springs Midland Road to north of Rock Springs Midland Road.
· Daily (excluding holiday restrictions), 9 a.m. – 3 p.m., There will be alternating lane and shoulder closures in both directions for new turn lane construction.
RUTHERFORD COUNTY – CNY020
The resurfacing on U.S. 41 (S.R.2) from U.S. 70S (S.R. 1) to near Kensington Square Court and on U.S 70 (S.R. 1) from south of Ash Street to near South Rutherford Boulevard
September 15th through September 21st, 8:00am to 4:00pm. There will be alternating lane closures on U.S. 41 (S.R.2) from U.S. 70S (S.R. 1) to near Kensington Square Court and on U.S 70 (S.R. 1) from south of Ash Street to near South Rutherford Boulevard for Head Walls and or Permanent Pavement Markings. At least one lane will open in each direction.