Road Construction Projects/Closures 4/18-4/24/2016

0
296

RUTHERFORD COUNTY, Resurfacing I-24 from Stones River Bridge (MM 78.5) to East of the Bridge over CSX Railroad (MM 82)

* Friday April 15, 8PM through Monday April 18, 5AM, There will be partial lane closures on the I-24 westbound on ramp at MM 81 (from Hwy 231, Church Street onto I-24 WB) for removal and replacement of concrete pavement. One lane will remain open to traffic. One of the northbound turning lanes on Church Street (US 231) to I-24 westbound will also be closed. This partial closure will remain in place until concrete reaches specified strength.

RUTHERFORD COUNTY, Grading, Drainage and Paving on SIA Route Serving Nissan North America

* From now through August 2016, Singer Road, from North Broad Street to the Nissan North America entrance, will be closed to through traffic. This closure will remain in place until the project has been completed or until 8/31/16. Local business access within the project limits will be provided.

* Friday April 15, 6:30AM to 7PM, Northbound North Broad Street shoulder will be closed at Singer Road, for work on overhead power lines. This closure will remain in place for Friday, April 15 only. Additionally, a rolling road block will be required for North Broad Street to allow new lines to be pulled across travel lanes.

RUTHERFORD and WILLIAMSON COUNTIES, Performance Based Maintenance Work on I-24, I-65, SR 840

* Thursday April 14 through Friday April 15, and Monday April 18 through Tuesday April 19, 7PM-5AM, There will be lane closures at various locations on SR 840 in both directions to allow for milling. There will be one lane open at all times in both directions.

* Thursday April 14 & Friday April 15, Monday April 18 through Wednesday April 20, 9AM – 3PM, There will be lane closures at various locations on SR 840 in both directions to allow for paving. There will be one lane open at all times in both directions.

* Monday April 15, 8PM-5AM, There will be alternating lane closures on I-65 in both directions between MM 66 (McEwen) and MM 71 (Concord Rd) for drain cleaning.

City of Murfreesboro Road Projects and Work

Bridge over Broad Street TDOT Project

Expected Lane Closures: Monday through Friday, 8:00 pm to 6:00 am: There will be alternating lane closures on NW Broad Street, Ridgley Road and W College Street for underground utility crossing. There will be lane shifts and traffic interruptions. Broadmor Blvd is closed to through traffic for utility crossing and general construction work.  W Lytle Street and a short segment of College St and Burton St are also closed to traffic for construction work. Retaining wall work continues as part of the southwest and southeast ramps for the new overpass.  Appropriate traffic controls will be in place.

Sewer Pump Station Project (NW Broad St at Battlefield Pkwy)

Expected Lane Closures: Monday through Friday, 6:00 am to 5 pm: Contractor for Water & Sewer Department will be installing sewer lines within TDOT right-of-way/Battlefield Pkwy. A small section of Battlefield Pkwy is closed. Underground bore work continues. Appropriate traffic controls will be in-place.

W Lytle Street Relocation Project (NW Broad St to Barker St)

Expected Lane Closures: Monday through Friday, 8:00 pm to 6:00 am: W Lytle Street is also closed to traffic at NW Broad Street for construction work.  Underground utility work continues.  Appropriate traffic controls will be in place.

Middle Tennessee Widening Project (Greenland Dr to E Main St)

Expected Lane Closures: Monday through Friday:  The contractor has implemented the next phase of the traffic control plan on Middle Tennessee Blvd.  Traffic on Middle Tennessee Blvd has been shifted to the east side and reduced to two lanes between E Main St and Greenland Dr (near the tennis courts).  E Lytle St is closed at Middle Tennessee Blvd.  The section of E Lytle St between N Bilbro Ave and Middle Tennessee Blvd are only open to local traffic.  Appropriate traffic controls and detours signs will be in place.

Murfreesboro Water & Sewer Rehabilitation Work

1) Sulphur Springs Rd between Haynes Dr and Victoria – 4/20 and 4/21
2) Sulphur Springs between Corner Ct and Ravenwood Dr – 4/18 to 4/22
3) Jetton Dr between Lokey Ave and E Hembree St – 4/20 to 4/23
4) Greenland Dr between Old Lascasss Rd and Brown Dr – 4/18 to 4/22 (night work 8 pm to 6 am)
5) Haynes Dr between Wendelwood Dr and 205 Haynes Dr – 4/20 and 4/21
6) Haynes Dr between 212 – 419 Haynes Dr – 4/20

Expected Lane Closures: Monday through Friday, 9:00 am to 3:00 pm: The contractor for Water & Sewer Department will be performing manhole rehabilitation/repairs of the sewer lines. Traffic will be reduced to one lane flagging operation. Appropriate traffic controls will be in place.

TDOT Roadway Improvement Project (Singer Road between NW Broad St and CSX Railroad)

Expected Lane Closures: Monday, March 14 – Wednesday, August 31:  The contractor for TDOT will be closing Singer Rd between NW Broad St and CSX Tracks to make roadway improvements.  Access to and from businesses and residents will be from Florence Road.  Appropriate traffic controls will be in place.

Private Development Roadway Improvement Work (Veterans Pkwy just north of Old Fort Pkwy)

Expected Minor Lane Closures: Monday through Friday, 9:00 am to 3:00 pm:  Contractor for a private development will be performing roadway improvement on Veterans Pkwy just north of Old Fort Pkwy.  There will be lane closures and traffic interruptions.  Appropriate traffic controls will be in place.

Private Development Roadway Improvement Work (New Salem Hwy just west of Saint Andrews Dr)

Expected Lane Closures: Monday through Friday, 9:00 am to 3:00 pm:  Contractor for a private development will be performing roadway improvement on New Salem Hwy just west of Saint Andrews Dr.  The shoulder along New Salem Hwy will be closed.  There will be minor traffic interruptions.  Appropriate traffic controls will be in place.

New Sewer Service Installation Work (Hickerson Dr between W Castle St and S Front St)

Expected Lane Closures: Monday through Friday, 8:30 am to 2:30 pm:  Contractor for a private development will be installing sewer service on Hickerson Dr.  There will be minor traffic interruptions.  Appropriate traffic controls will be in place.

Rutherford County Judicial Center Project (Burton St/Church St)

Expected Lane Closures: Tuesday, 8:00 am to 3:00 pm: Construction crews will be removing a tree on Burton St between Maple St and Church St.  There will be lane closures and traffic interruptions.  Appropriate traffic controls and detours will be in place.

Annual City Street Paving Project

Expected Lane Closures:  Monday through Friday, 9:00 AM – 3:00 PM:  City paving contractor will be milling/paving the following streets:  Avenal Ct, Crown Hill Dr, Northwoods Cove, Henry Hall, Victoria Dr, Cornwall Ct, Leeds Ct, Rye Ct, Langtry Ct, Fairfax Dr, Flower Park, Jackson Rd & General Kirk Dr.  There will be lane closures and traffic interruptions.  Appropriate traffic controls will be in-place.

 

Please Join Our FREE Newsletter!