Murfreesboro Road Construction Projects: April 29-May 4

0
145

Middle Tennessee Widening Project (Greenland Dr to E. Main St)

Expected Lane Closures: Monday through Friday: Median construction, traffic signal and landscaping work continues between E Main St and Greenland Dr. Final paving and pavement marking work continues. Appropriate traffic controls are in place.

W Lytle Street Roadway Improvement Project (Baker St to Church St)

Expected Lane Closures: Monday through Friday: W Lytle St is re-opened to traffic. Incidental construction work continues along W Lytle St. Appropriate traffic controls are in place.

Private Development (Circle K) Turn Lane Improvement Work (John Bragg Hwy just east of Rutherford Blvd)

Expected Lane Closures: Monday through Friday, 8:30 am to 3:30 pm: As part of private development, turn lane and median modifications will be done on John Bragg Hwy just east of Rutherford Blvd. There will be lane closures and minor traffic interruptions. Appropriate traffic controls will be in place.

Private Development (Starbucks) Driveway Improvement Work (Cason Ln and River Rock Blvd)

Expected Lane Closures: Monday through Friday, 8:30 am to 3:00 pm: As part of private development, driveway and curb & gutter work will be done along River Rock Blvd and Cason Ln. There will be short lane closures and minor traffic interruptions. Appropriate traffic controls will be in place.

Right Turn Lane Improvement Work (Rutherford Blvd at Mercury Blvd)

Expected Lane Closures: Monday through Friday, 8:30 am to 3:00 pm: City contractor will be making right turn lane improvements on Rutherford Blvd (southbound) at Mercury Blvd. There will be minor lane closures and traffic interruptions. Northbound traffic will not be affected. Appropriate traffic controls will be in place.

Underground Sewer Line/Manhole Installation Work (Victory Station Way between Battalion Way and Swanholme Dr)

Expected Road Closures: April 23 through May 7: Victory Station Way will be closed to through traffic for sewer line installing work. Access to business and residential driveways will be kept open at all times. Appropriate traffic controls will be in place.

Curb & Gutter Removal and Installation Work (Medical Center Pkwy just west of Maplegrove Dr)

Expected Lane Closures: Tuesday, 9:00 am to 3:00 pm: Contractor for private development will be removing Curb & Gutter along Medical Center Pkwy just west of Maplegrove Dr. There will be lane closures and traffic interruptions. Appropriate traffic controls will be in place.

Underground Utility Installation Work (Garrison Dr between Gateway Blvd and W College St)

Expected No Closures: Monday through Friday, 9:00 am to 3:00 pm: Utility contractor will be installing underground utility lines along Garrison Dr. There will be minor traffic interruptions and no lane closures on Garrison Dr. Appropriate traffic controls will be in place.

Annual City Street Paving Projects

Expected Lane Closures: Monday through Friday, 9:00 AM – 3:00 PM: City paving contractor will be loop installation, milling, paving and striping on the following streets:
1. Molloy Ln at New Salem Hwy
2. Middle Tennessee Blvd between E Main St and Greenland Dr
3. Old Fort Pkwy at John R Rice Blvd ( night time work between 8:00 pm and 6:00 am, 4/26 – 4/30)
Expect lane shifts and traffic interruptions. Appropriate traffic controls will be in place.

TDOT Resurfacing Projects

SR 99 (New Salem Hwy) resurfacing from Cason Lane to I-24
• Daily, 9AM-4PM, There will be alternating lane closures between the intersection of Barfield Drive and SR99 for the placement of bridge beams over West Fork Stones River. Appropriate traffic controls will be in-place.